Which of the following input switches is the most applicable to the UPS5000-E 100 kVA?

  1. 80 A
  2. 125 A
  3. 160 A
  4. 200 A

Answer(s): D



Which of the following basic project information doesn't need to be entered manually before configuration quotation? ()

  1. Quotation No.
  2. Quotation name
  3. Representative office
  4. Customer name

Answer(s): A



The UPS5000-E power module adopts fan fault-tolerant design. When two fans are faulty, how many loads in percentage is this power module still be able to carry?

  1. 0.25
  2. 0.3
  3. 0.5
  4. 0.6

Answer(s): B



Which of the following alarms can the UPS5000-A dry contact expansion card set? (Multiple Choice)

  1. Bypass power supply
  2. Battery supply
  3. Battery undervoltage
  4. G. controlling
  5. Door sensor

Answer(s): A,B,C,D,E



The UPS5000-E battery adopts the design without neutral wire, which facilitates battery re-utilization in the replacement of a tower-mounted UPS.

  1. TRUE
  2. FALSE

Answer(s): B