QUESTION: 22
What are the development phases defined by the Formal Project Management process
template?

A. Inception, Elaboration, Construction, Transition
B. Inception, Definition, Construction, Transition
C. Design, Implementation, Testing, Deployment
D. Requirements, Design, Implementation, Testing

Answer(s): D
QUESTION: 23
Which three automated notification methods are used to inform users that a work item has been
changed? (Choose three.)

A. email
B. font color in the work item
C. events feed
D. instant message
E. pop-up in the Eclipse client

Answer(s): A, C, E
QUESTION: 24
What does the permission indicated below in the Team Configuration of a Project Area Editor
allow role members to do? Team Configuration-> Source Control->Replicate change sets-
>replicate