Which of the following statements is correct regarding the assessment of risk in the annual audit planning process?
1. Activities requested by management should be considered higher risk than those requested by the audit committee.
2. Activities with lower budgets can be as high risk as those with higher budgets.
3. The potential financial or adverse exposure should always be considered in the assessment of risk.

  1. 1 only
  2. 2 only
  3. 3 only
  4. 2 and 3 only

Answer(s): D



Management has asked the internal audit activity to perform an operational audit of a division that recently reported an increase in expenditures in addition to a decrease in profits. However, existing internal audit resources are currently engaged in a legal compliance audit. Which factor would be considered least important in deciding whether resources should be removed from the legal compliance audit to the operational audit?

  1. The increase in expenditures at the division over the past year.
  2. The probability that the legal compliance audit will detect fraud.
  3. The results of the external auditor's most recent financial audit.
  4. The potential for regulatory fines associated with the legal compliance audit.

Answer(s): C



Given the scarcity of internal audit resources, a chief audit executive (CAE) decides not to schedule a follow-up of audit recommendations when developing engagement work schedules.
Why does the CAE's decision violate the Standards?

  1. It is not the CAE's responsibility to establish a process for a follow-up.
  2. Lack of resources is not a sufficient reason to forgo a follow-up.
  3. Follow-up actions should take priority over new engagements in scheduling.
  4. When resources are scarce, the follow-up can be incorporated into the next engagement.

Answer(s): B



As part of a preliminary survey of the purchasing function, an internal auditor reads the department's policies and procedures manual and concludes that the manual describes the processing steps clearly and contains an appropriate internal control design. The next engagement objective is to evaluate the operating effectiveness of internal controls. Which procedure would fulfill this objective most effectively?

  1. Perform a design test.
  2. Perform a compliance test.
  3. Perform a systems test.
  4. Perform an efficiency test.

Answer(s): B



Page 70 of 128



Post your Comments and Discuss IIA IIA-CIA-Part2 exam with other Community members:

NOOR commented on October 06, 2024
I want to pass my CIA Exam P2 withing the next 2weeks, can I get help?
UNITED ARAB EMIRATES
upvote

ET commented on August 19, 2024
I have just failed my CIA 2 second attempt today. May I have any assistance from you guys?
Anonymous
upvote