Free IIA-CIA-Part3 Exam Braindumps (page: 27)

Page 27 of 390

The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc., are presented below. The numbers in the diagram are the expected times (in days) to perform each activity in the project.


The expected time of the critical path is:

  1. 12.0 days
  2. 13.0 days
  3. 11.5 days
  4. 11.0 days

Answer(s): B

Explanation:

The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days (5.5 + 7.5) based on expected times.



To keep costs at a minimum and decrease the completion time by 1-1/2 days, Networks, Inc.
should crash activity(ies):

  1. AD and AB
  2. DE
  3. AD
  4. AB and CE

Answer(s): A

Explanation:

The critical (longest) path is A-D-E, which has an expected time of 13 days (5.5 + 7.5). However, to decrease the project's completion time by 1.5 days, paths A-B-C-E (4.5 + 1.0 + 6.5 = 12 days) and A-B-D-E (4.5 + .5 + 7.5= 12.5 days) as well as A-D-E must also be shortened. Hence, A-D-E must be reduced by 1.5 days. A-B-C-E by .5 day, and A-B-D-E by 1.0 day. The only way to decrease A-D-E by 1.5 days is to crash activity AD (5.5 expected time - 4.0 crash time = 1.5 days). Crashing DE results in a 1.0-day saving (7.5-6.5) only. Crashing AB is the efficient way to reduce both A-B-C-E and A-B-D-E by the desired amount of time because it is part of both paths. The incremental cost of crashing AB is US $1,000 (US $4,000 crash cost - US $3,000 normal cost) to shorten the completion time by 1.0 day (4.5 - 3.5). The alternatives for decreasing both A-B-C-E and A-B-D-E are more costly.



When making a cost-time trade-off in CPM analysis, the first activity that should be crashed is the activity:

  1. With the largest amount of slack.
  2. With the lowest unit crash cost.
  3. On the critical path with the maximum possible time reduction.
  4. On the critical path with the lowest unit crash cost.

Answer(s): D

Explanation:

When making a cost-time trade-off, the first activity to be crashed (have its completion time accelerated) is one on the critical path. To select an activity on another path would not reduce the total time of completion. The initial activity chosen should be the one with the completion time that can be accelerated at the lowest possible cost per unit of time saved.



In PERT, slack is the:

  1. Uncertainty associated with time estimates.
  2. Difference between the latest starting time and earliest finishing time.
  3. Path that has the largest amount of time associated with it.
  4. Number of days an activity can be delayed without forcing a delay for the entire project.

Answer(s): D

Explanation:

Slack is the amount of time that commencement of an activity can be delayed without forcing a delay of the entire project.



Page 27 of 390



Post your Comments and Discuss IIA IIA-CIA-Part3 exam with other Community members:

Gosia commented on December 16, 2024
Hi, did you have the same questions on exams?
POLAND
upvote

Becky commented on June 23, 2024
Exam collections here awesome. Kudos
Anonymous
upvote

Shehata mohamed commented on December 13, 2023
Many thanks cia part 3
Anonymous
upvote

IIA-CIA-Part3 commented on July 16, 2023
CIA Exam Part Three: Business Knowledge for Internal Auditing
Anonymous
upvote

KC commented on December 20, 2017
Very helpful. For a another braindump I paid almost 4 times this and got the same material. Then I came across this site. Can't believe the same set of questions and answers are sold for almost a fraction of a price with much better quality and support.
UNITED STATES
upvote