Under throughput costing, the only cost considered to be truly variable in the short run is:

  1. Direct materials.
  2. Direct labor.
  3. Manufacturing overhead.
  4. All manufacturing costs are considered variable.

Answer(s): D

Explanation:

Throughput costing, also called super variable costing, recognizes only direct materials costs as being truly variable and thus relevant to the calculation of throughput margin.



The immediate goal of a theory of constraints (TOC) analysis is to:

  1. Maximize the efficiency of the entire production process.
  2. Minimize direct materials cost.
  3. Maximize contribution margin through the constraint.
  4. Smooth production flow to eliminate backup in the system.

Answer(s): C

Explanation:

A basic principle of TOC analysis is that short-term profit maximization requires maximizing the contribution margin through the constraint, called the throughput margin or throughput contribution.



In a theory of constraints (TOC) analysis, the bottleneck operation (the constraint) corresponds to which part of the drum-buffer-rope model?

  1. Drum.
  2. Buffer.
  3. Rope.
  4. No part of TOC analysis corresponds to the drum-buffer-rope model.

Answer(s): B

Explanation:

Production flow through a constraint is managed using the drum-buffer-rope (DBR) system. The drum (i.e., the beat to which a production process marches) is the bottleneck operation. The constraint sets the pace for the entire process. The buffer is a minimal amount of work-in-process input to the drum that is maintained to ensure that it is always in operation. The rope is the sequence of activities preceding and including the bottleneck operation that must be coordinated to avoid inventory buildup.



The process model used in a theory of constraints (TOC) analysis is called:

  1. Just-in-time.
  2. Drum-buffer-rope.
  3. Materials requirements planning.
  4. Lean production.

Answer(s): B

Explanation:

Production flow through a constraint is managed using the drum-buffer-rope (DBR) system. The drum (i.e.. the beat to which a production process marches) is the bottleneck operation. The constraint sets the pace for the entire process. The buffer is a minimal amount of work-in-process input to the drum that is maintained to ensure that it is always in operation. The rope is the sequence of activities preceding and including the bottleneck operation that must be coordinated to avoid inventory buildup.



Page 33 of 390



Post your Comments and Discuss IIA IIA-CIA-Part3 exam with other Community members:

Gosia commented on December 16, 2024
Hi, did you have the same questions on exams?
POLAND
upvote

Becky commented on June 23, 2024
Exam collections here awesome. Kudos
Anonymous
upvote

Shehata mohamed commented on December 13, 2023
Many thanks cia part 3
Anonymous
upvote

IIA-CIA-Part3 commented on July 16, 2023
CIA Exam Part Three: Business Knowledge for Internal Auditing
Anonymous
upvote

KC commented on December 20, 2017
Very helpful. For a another braindump I paid almost 4 times this and got the same material. Then I came across this site. Can't believe the same set of questions and answers are sold for almost a fraction of a price with much better quality and support.
UNITED STATES
upvote