One of the processes within requirements analysis is to prioritize requirements. As a business analyst why would you ever want to prioritize requirements?

  1. You may need to determine the cost of each requirement.
  2. You may need to determine the schedule for each requirement.
  3. You may need to determine which requirements are most critical so the analysis and implementation efforts focus on the most critical requirements.
  4. You may need to determine which requirements are most critical so additional risk analysis can be completed on those requirements.

Answer(s): C



You are the business analyst for your organization and are working with Jennifer to conduct stakeholder analysis. You would like to create a RACI chart to help with the roles of the people involved in the stakeholder analysis process. Jennifer is not familiar with this chart and asks what does RACI mean.
Which one of the following best describes the RACI chart in the conduct stakeholder analysis process?

  1. It's a matrix that uses the Responsible, Accountable, Consult, and Inform tasks as part of the stakeholder analysis process.
  2. It's a role and responsibility chart that identifies when stakeholders are needed in the business analyst duties.
  3. It's a matrix that uses Role, Action, Consult, and Inform as part of the conduct stakeholder analysis process.
  4. It's a rule that the business analyst can use to identify all of the needed stakeholders: roles, actions, communications, and interest.

Answer(s): A



You are the business analyst for your organization. Management wants you to prioritize the identified requirements by the requirements that have the highest likelihood of success.

Why would management want you to prioritize the requirements with this factor even though some of the requirements may be difficult to implement?

  1. They want a fast return on investment.
  2. They want to show early success in the implementation to the project stakeholders.
  3. They don't understand the requirements.
  4. They want to avoid penalties or fines due to a pending law.

Answer(s): B



You are creating the solution scope for an identified problem in your organization. You are working with several stakeholders during this process including the domain subject matter expert, the implementation subject matter expert, the project manager, and the sponsor.

Which of these stakeholders will be responsible for writing the project scope?

  1. Domain subject matter expert
  2. Business analyst
  3. Project manager
  4. Sponsor

Answer(s): C