Which of the following controls do NOT come under technical class of control?

  1. Program management control
  2. System and Communications Protection control
  3. Identification and Authentication control
  4. Access Control

Answer(s): A

Explanation:

Program Management control comes under management class of controls, not technical.
Program Management control is driven by the Federal Information Security Management Act (FISMA). It provides controls to ensure compliance with FISMA. These controls complement other controls. They don't replace them.

Incorrect Answers:
B, C, D: These controls comes under technical class of control.

The Technical class of controls includes four families. These families include over 75 individual controls. Following is a list of each of the families in the Technical class:
Access Control (AC): This family of controls helps an organization implement effective access control. They ensure that users have the rights and permissions they need to perform their jobs, and no more. It includes principles such as least privilege and separation of duties.
Audit and Accountability (AU): This family of controls helps an organization implement an effective audit program. It provides details on how to determine what to audit. It provides details on how to protect the audit logs. It also includes information on using audit logs for non-repudiation.
Identification and Authentication (IA): These controls cover different practices to identify and authenticate users. Each user should be uniquely identified. In other words, each user has one account. This account is only used by one user. Similarly, device identifiers uniquely identify devices on the network.
System and Communications Protection (SC): The SC family is a large group of controls that cover many aspects of protecting systems and communication channels. Denial of service protection and boundary protection controls are included. Transmission integrity and confidentiality controls are also included.



Mary is a project manager in her organization. On her current project she is working with her project team and other key stakeholders to identify the risks within the project. She is currently aiming to create a comprehensive list of project risks so she is using a facilitator to help generate ideas about project risks. What risk identification method is Mary likely using?

  1. Delphi Techniques
  2. Expert judgment
  3. Brainstorming
  4. Checklist analysis

Answer(s): C

Explanation:

Mary is using brainstorming in this example. Brainstorming attempts to create a comprehensive list of risks and often is led by a moderator or facilitator to move the process along.
Brainstorming is a technique to gather general data. It can be used to identify risks, ideas, or solutions to issues by using a group of team members or subject-matter expert. Brainstorming is a group creativity technique that also provides other benefits, such as boosting morale, enhancing work enjoyment, and improving team work.

Incorrect Answers:
A: The Delphi technique uses rounds of anonymous surveys to generate a consensus on the identified risks.

B: Expert judgment is not the best answer for this; projects experts generally do the risk identification, in addition to the project team.

D: Checklist analysis uses historical information and information from similar projects within the organization's experience.



Which of the following is an administrative control?

  1. Water detection
  2. Reasonableness check
  3. Data loss prevention program
  4. Session timeout

Answer(s): C



You are the project manager of the NHH Project. You are working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team. What document do you and your team is creating in this scenario?

  1. Project plan
  2. Resource management plan
  3. Project management plan
  4. Risk management plan

Answer(s): D

Explanation:

The risk management plan, part of the comprehensive management plan, defines how risks will be identified, analyzed, monitored and controlled, and even responded to.

A Risk management plan is a document arranged by a project manager to estimate the effectiveness, predict risks, and build response plans to mitigate them. It also consists of the risk assessment matrix.

Risks are built in with any project, and project managers evaluate risks repeatedly and build plans to address them. The risk management plan consists of analysis of possible risks with both high and low impacts, and the mitigation strategies to facilitate the project and avoid being derailed through which the common problems arise. Risk management plans should be timely reviewed by the project team in order to avoid having the analysis become stale and not reflective of actual potential project risks. Most critically, risk management plans include a risk strategy for project execution.

Incorrect Answers:
A: The project plan is not an official PMBOK project management plan.

B: The resource management plan defines the management of project resources, such as project team members, facilities, equipment, and contractors.

C: The project management plan is a comprehensive plan that communicates the intent of the project for all project management knowledge areas.



Page 11 of 451



Post your Comments and Discuss ISACA CRISC exam with other Community members:

Fei commented on November 26, 2024
Very good resources
UNITED STATES
upvote

Yingying Li commented on December 02, 2023
Very useful practice tests.
Anonymous
upvote

Stephen commented on August 27, 2023
Can you please share CIMAPRA19-FO2-1 Exam dumps please
Anonymous
upvote

Parsad commented on June 04, 2023
Thank you for the buy 1 get 1 free discount. This helped me a lot. I donot have a lot of money.
INDIA
upvote

Petros commented on May 01, 2023
I could not have passed my certification test without the help of this study guide - highly recommend it!
PORTUGAL
upvote

Bobby commented on January 18, 2022
Passed easily.
UNITED STATES
upvote

Santosh commented on January 29, 2020
Passed my exam today with a score of 798. This is good material.
INDIA
upvote

Arron commented on January 26, 2020
This saved me so much time. The questions and answers are adequate and close to real exam. I like the PDF and its format. Just put it on my iPad and studied while traveling to work. This was my first time using this site and I am pretty happy about their service and price.
GERMANY
upvote

Suresh commented on April 17, 2019
This download is a waste of time . I downloaded the windows app and installed and it is asking to load the test. No documentation provided on how to use the desk top tool. Unable to install on my MAC not Iphone compatible. RE- Admin: Suresh, our website clearly says that the Test Engine software is for Windows only. We have not advertised anywhere in our website saying the Test Engine Software is for MAC as well.
UNITED STATES
upvote