Where are all risks and risk responses documented as the project progresses?

  1. Risk management plan
  2. Project management plan
  3. Risk response plan
  4. Risk register

Answer(s): D

Explanation:

All risks, their responses, and other characteristics are documented in the risk register. As the project progresses and the conditions of the risk events change, the risk register should be updated to reflect the risk conditions.

Incorrect Answers:
A: The risk management plan addresses the project management's approach to risk management, risk identification, analysis, response, and control.

B: The project management plan is the overarching plan for the project, not the specifics of the risk responses and risk identification.

C: The risk response plan only addresses the planned risk responses for the identified risk events in the risk register.



A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?

  1. Transference
  2. Mitigation
  3. Avoidance
  4. Exploit

Answer(s): A

Explanation:

When you are hiring a third party to own risk, it is known as transference risk response.

Risk transfer means that impact of risk is reduced by transferring or otherwise sharing a portion of the risk with an external organization or another internal entity. Transfer of risk can occur in many forms but is most effective when dealing with financial risks. Insurance is one form of risk transfer.

Incorrect Answers:
B: The act of spending money to reduce a risk probability and impact is known as mitigation.

C: When extra activities are introduced into the project to avoid the risk, this is an example of avoidance.

D: Exploit is a strategy that may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized.



John works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks associated to the time allowances for the activities or projects as a whole, with a width of the range indicating the degrees of risk?

  1. Activity duration estimates
  2. Activity cost estimates
  3. Risk management plan
  4. Schedule management plan

Answer(s): A

Explanation:

The activity duration estimates review is valuable in identifying risks associated to the time allowances for the activities or projects as a whole, with a width of the range indicating the degrees of risk.

Incorrect Answers:
B: The activity cost estimates review is valuable in identifying risks as it provides a quantitative assessment of the expected cost to complete scheduled activities and is expressed as a range, with a width of the range indicating the degrees of risk.

C: A Risk management plan is a document arranged by a project manager to estimate the effectiveness, predict risks, and build response plans to mitigate them. It also consists of the risk assessment matrix.

D: It describes how the schedule contingencies will be reported and assessed.



Which of the following events refer to loss of integrity?
Each correct answer represents a complete solution. Choose three.

  1. Someone sees company's secret formula
  2. Someone makes unauthorized changes to a Web site
  3. An e-mail message is modified in transit
  4. A virus infects a file

Answer(s): B,C,D

Explanation:

Loss of integrity refers to the following types of losses:
An e-mail message is modified in transit A virus infects a file Someone makes unauthorized changes to a Web site

Incorrect Answers:
A: Someone sees company's secret formula or password comes under loss of confidentiality.



Page 12 of 451



Post your Comments and Discuss ISACA CRISC exam with other Community members:

Fei commented on November 26, 2024
Very good resources
UNITED STATES
upvote

Yingying Li commented on December 02, 2023
Very useful practice tests.
Anonymous
upvote

Stephen commented on August 27, 2023
Can you please share CIMAPRA19-FO2-1 Exam dumps please
Anonymous
upvote

Parsad commented on June 04, 2023
Thank you for the buy 1 get 1 free discount. This helped me a lot. I donot have a lot of money.
INDIA
upvote

Petros commented on May 01, 2023
I could not have passed my certification test without the help of this study guide - highly recommend it!
PORTUGAL
upvote

Bobby commented on January 18, 2022
Passed easily.
UNITED STATES
upvote

Santosh commented on January 29, 2020
Passed my exam today with a score of 798. This is good material.
INDIA
upvote

Arron commented on January 26, 2020
This saved me so much time. The questions and answers are adequate and close to real exam. I like the PDF and its format. Just put it on my iPad and studied while traveling to work. This was my first time using this site and I am pretty happy about their service and price.
GERMANY
upvote

Suresh commented on April 17, 2019
This download is a waste of time . I downloaded the windows app and installed and it is asking to load the test. No documentation provided on how to use the desk top tool. Unable to install on my MAC not Iphone compatible. RE- Admin: Suresh, our website clearly says that the Test Engine software is for Windows only. We have not advertised anywhere in our website saying the Test Engine Software is for MAC as well.
UNITED STATES
upvote