Fred is the project manager of a large project in his organization. Fred needs to begin planning the risk management plan with the project team and key stakeholders. Which plan risk management process tool and technique should Fred use to plan risk management?

  1. Information gathering techniques
  2. Data gathering and representation techniques
  3. Planning meetings and analysis
  4. Variance and trend analysis

Answer(s): C

Explanation:

There is only one tool and technique available for Fred to plan risk management: planning meetings and analysis. Planning Meeting and Analysis is a tool and technique in the Plan Risk Management process. Planning meetings are organized by the project teams to develop the risk management plan. Attendees at these meetings include the following:

Project manager
Selected project team members Stakeholders
Anybody in the organization with the task to manage risk planning

Sophisticated plans for conducting the risk management activities are defined in these meetings, responsibilities related to risk management are assigned, and risk contingency reserve application approaches are established and reviewed.

Incorrect Answers:
A, B, D: These are not plan risk management tools and techniques.



Which of the following is the HIGHEST risk of a policy that inadequately defines data and system ownership?

  1. User management coordination does not exist
  2. Audit recommendations may not be implemented
  3. Users may have unauthorized access to originate, modify or delete data
  4. Specific user accountability cannot be established

Answer(s): C

Explanation:

There is an increased risk without a policy defining who has the responsibility for granting access to specific data or systems, as one could gain system access without a justified business needs. There is better chance that business objectives will be properly supported when there is appropriate ownership.

Incorrect Answers:
A, B, D: These risks are not such significant as compared to unauthorized access.



Marie has identified a risk event in her project that needs a mitigation response. Her response actually creates a new risk event that must now be analyzed and planned for. What term is given to this newly created risk event?

  1. Residual risk
  2. Secondary risk
  3. Infinitive risk
  4. Populated risk

Answer(s): B

Explanation:

Secondary risks are the risks that come about as a result of implementing a risk response. This new risk event must be recorded, analyzed, and planned for management.

Incorrect Answers:
A: A residual risk event is similar to a secondary risk, but is often small in probability and impact, so it may just be accepted.

C: Infinitive risk is not a valid project management term.

D: Populated risk event is not a valid project management term.



Which one of the following is the only output for the qualitative risk analysis process?

  1. Project management plan
  2. Risk register updates
  3. Organizational process assets
  4. Enterprise environmental factors

Answer(s): B

Explanation:

Risk register update is the only output of the choices presented for the qualitative risk analysis process. The four inputs for the qualitative risk analysis process are the risk register, risk management plan, project scope statement, and organizational process assets. The output of perform qualitative risk analysis process is Risk Register Updates. Risk register is updated with the information from perform qualitative risk analysis and the updated risk register is included in the project documents. Updates include the following important elements:
Relative ranking or priority list of project risks Risks grouped by categories
Causes of risk or project areas requiring particular attention List of risks requiring response in the near-term
List of risks for additional analysis and response Watchlist of low priority risks
Trends in qualitative risk analysis results

Incorrect Answers:
A, C, D: These are not the valid outputs for the qualitative risk analysis process.



Page 26 of 451



Post your Comments and Discuss ISACA CRISC exam with other Community members:

Fei commented on November 26, 2024
Very good resources
UNITED STATES
upvote

Yingying Li commented on December 02, 2023
Very useful practice tests.
Anonymous
upvote

Stephen commented on August 27, 2023
Can you please share CIMAPRA19-FO2-1 Exam dumps please
Anonymous
upvote

Parsad commented on June 04, 2023
Thank you for the buy 1 get 1 free discount. This helped me a lot. I donot have a lot of money.
INDIA
upvote

Petros commented on May 01, 2023
I could not have passed my certification test without the help of this study guide - highly recommend it!
PORTUGAL
upvote

Bobby commented on January 18, 2022
Passed easily.
UNITED STATES
upvote

Santosh commented on January 29, 2020
Passed my exam today with a score of 798. This is good material.
INDIA
upvote

Arron commented on January 26, 2020
This saved me so much time. The questions and answers are adequate and close to real exam. I like the PDF and its format. Just put it on my iPad and studied while traveling to work. This was my first time using this site and I am pretty happy about their service and price.
GERMANY
upvote

Suresh commented on April 17, 2019
This download is a waste of time . I downloaded the windows app and installed and it is asking to load the test. No documentation provided on how to use the desk top tool. Unable to install on my MAC not Iphone compatible. RE- Admin: Suresh, our website clearly says that the Test Engine software is for Windows only. We have not advertised anywhere in our website saying the Test Engine Software is for MAC as well.
UNITED STATES
upvote