Which among the following is the MOST crucial part of risk management process?

  1. Risk communication
  2. Auditing
  3. Risk monitoring
  4. Risk mitigation

Answer(s): A

Explanation:

Risk communication is a critical part in the risk management process. People are naturally uncomfortable talking about risk and tend to put off admitting that risk is involved and communicating about issues; incidents; and; eventually, even crises.

If risk is to be managed and mitigated, it must first be discussed and effectively communicated throughout an enterprise.

Incorrect Answers:
B: Auditing is done to test the overall risk management process and the planned risk responses. So it is the very last phase after completion of risk management process.

C: Risk monitoring is the last phase to complete risk management process, and for proper management of risk it should be communicated properly. Hence risk communication is the most crucial step.

D: Risk mitigation is one of the phases of risk management process for effective mitigation of risk it should be first communicated throughout an enterprise.



Which of the following is a key component of strong internal control environment?

  1. RMIS
  2. Segregation of duties
  3. Manual control
  4. Automated tools

Answer(s): B

Explanation:

Segregation of duties (SOD) is a key component to maintaining a strong internal control environment because it reduces the risk of fraudulent transactions. When duties for a business process or transaction are segregated it becomes more difficult for fraudulent activity to occur because it would involve collusion among several employees.

Incorrect Answers:
A: An RMIS can be a very effective tool in monitoring all risk factors that impact the enterprise. The danger is that many important classes of risk may be omitted from consideration by the system. hence it doesn't ensure strong internal control environment.

C: Manual controls usually not form strong internal control environment. By not automating SOD controls, there is, potentially, the issue of these controls becoming a barrier in serving the customer. As manual authorizations are often time consuming and require another step in any business process, this takes time away from serving the customer.

Automated compliance solutions aim to provide enterprises with timely and efficient internal controls that do not disrupt their normal business process.

D: It is not directly related in maintaining strong internal control environment. The automated tools are typically used to address SOD and also to provide the enterprise with reporting functionality on SOD violations (i.e., detective controls) and to put in place preventive controls.



You are the project manager of the NKJ Project for your company. The project's success or failure will have a significant impact on your organization's profitability for the coming year. Management has asked you to identify the risk events and communicate the event's probability and impact as early as possible in the project.
Management wants to avoid risk events and needs to analyze the cost-benefits of each risk event in this project. What term is assigned to the low-level of stakeholder tolerance in this project?

  1. Mitigation-ready project management
  2. Risk avoidance
  3. Risk utility function
  4. Risk-reward mentality

Answer(s): C

Explanation:

Risk utility function is assigned to the low-level of stakeholder tolerance in this project.

The risk utility function describes a person's or organization's willingness to accept risk. It is synonymous with stakeholder tolerance to risk.

Risk utility function facilitates the selection and acceptance of risk and provides opportunity to merge the approach with setting thresholds of risk acceptability and using utility-risk ratios if necessary.

Incorrect Answers:
A: This is not a valid project management and risk management term. B: Risk avoidance is a risk response to avoid negative risk events.
D: Risk-reward describes the balance between accepting risks and the expected reward for the risk event. Risk-reward mentality is not a valid project management term.



How residual risk can be determined?

  1. By determining remaining vulnerabilities after countermeasures are in place.
  2. By transferring all risks.
  3. By threat analysis
  4. By risk assessment

Answer(s): A



Page 54 of 451



Post your Comments and Discuss ISACA CRISC exam with other Community members:

Fei commented on November 26, 2024
Very good resources
UNITED STATES
upvote

Yingying Li commented on December 02, 2023
Very useful practice tests.
Anonymous
upvote

Stephen commented on August 27, 2023
Can you please share CIMAPRA19-FO2-1 Exam dumps please
Anonymous
upvote

Parsad commented on June 04, 2023
Thank you for the buy 1 get 1 free discount. This helped me a lot. I donot have a lot of money.
INDIA
upvote

Petros commented on May 01, 2023
I could not have passed my certification test without the help of this study guide - highly recommend it!
PORTUGAL
upvote

Bobby commented on January 18, 2022
Passed easily.
UNITED STATES
upvote

Santosh commented on January 29, 2020
Passed my exam today with a score of 798. This is good material.
INDIA
upvote

Arron commented on January 26, 2020
This saved me so much time. The questions and answers are adequate and close to real exam. I like the PDF and its format. Just put it on my iPad and studied while traveling to work. This was my first time using this site and I am pretty happy about their service and price.
GERMANY
upvote

Suresh commented on April 17, 2019
This download is a waste of time . I downloaded the windows app and installed and it is asking to load the test. No documentation provided on how to use the desk top tool. Unable to install on my MAC not Iphone compatible. RE- Admin: Suresh, our website clearly says that the Test Engine software is for Windows only. We have not advertised anywhere in our website saying the Test Engine Software is for MAC as well.
UNITED STATES
upvote