Free CRISC Exam Braindumps (page: 61)

Page 61 of 451

Tom works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks, and provides a quantitative assessment of the likely cost to complete the scheduled activities?

  1. Activity duration estimates
  2. Risk management plan
  3. Cost management plan
  4. Activity cost estimates

Answer(s): D

Explanation:

The activity cost estimates review is valuable in identifying risks as it provides a quantitative assessment of the expected cost to complete the scheduled activities and is expressed as a range, with a width of the range indicating the degrees of risk.

Incorrect Answers:
A: The activity duration estimates review is valuable in identifying risks associated to the time allowances for the activities or projects as a whole, with a width of the range indicating the degrees of risk.

B: This is the output of plan risk management process. A Risk management plan is a document arranged by a project manager to estimate the effectiveness, predict risks, and build response plans to mitigate them. It also consists of the risk assessment matrix.

C: The cost management plan sets how the costs on a project are managed during the project's lifecycle. It defines the format and principles by which the project costs are measured, reported, and controlled. The cost management plan identifies the person responsible for managing costs, those who have the authority to approve changes to the project or its budget, and how cost performance is quantitatively calculated and reported upon.



Which of the following baselines identifies the specifications required by the resource that meet the approved requirements?

  1. Functional baseline
  2. Allocated baseline
  3. Product baseline
  4. Developmental baseline

Answer(s): B

Explanation:

Allocated baseline identifies the specifications that meet the approved requirements. Incorrect Answers:
A: Functional baseline identifies the initial specifications before any changes are made.

C: Product baseline identifies the minimal specification required by the resource to meet business outcomes.

D: Developmental baseline identifies the state of the resources as it is developed to meet or exceed expectations and requirements.



Which of the following nodes of the decision tree analysis represents the start point of decision tree?

  1. Decision node
  2. End node
  3. Event node
  4. Root node

Answer(s): D

Explanation:

Root node is the starting node in the decision tree. Incorrect Answers:
A: Decision nodes represents the choice available to the decision maker, usually between a risky choice and its non-risky counterpart.

C: Event node represents the possible uncertain outcomes of a risky decision, with at least two nodes to illustrate the positive and negative range of events.

B: End node represents the outcomes of risk and decisions.



You are the project manager of the NHH Project. You are working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team.
What document do you and your team is creating in this scenario?

  1. Project plan
  2. Resource management plan
  3. Project management plan
  4. Risk management plan

Answer(s): D

Explanation:

The risk management plan, part of the comprehensive management plan, defines how risks will be identified, analyzed, monitored and controlled, and even responded to.

A Risk management plan is a document arranged by a project manager to estimate the effectiveness, predict risks, and build response plans to mitigate them. It also consists of the risk assessment matrix.
Risks are built in with any project, and project managers evaluate risks repeatedly and build plans to address them. The risk management plan consists of analysis of possible risks with both high and low impacts, and the mitigation strategies to facilitate the project and avoid being derailed through which the common problems arise. Risk management plans should be timely reviewed by the project team in order to avoid having the analysis become stale and not reflective of actual potential project risks. Most critically, risk management plans include a risk strategy for project execution.

Incorrect Answers:
A: The project plan is not an official PMBOK project management plan.

B: The resource management plan defines the management of project resources, such as project team members, facilities, equipment, and contractors.

C: The project management plan is a comprehensive plan that communicates the intent of the project for all project management knowledge areas.



Page 61 of 451



Post your Comments and Discuss ISACA CRISC exam with other Community members:

Fei commented on November 26, 2024
Very good resources
UNITED STATES
upvote

Yingying Li commented on December 02, 2023
Very useful practice tests.
Anonymous
upvote

Stephen commented on August 27, 2023
Can you please share CIMAPRA19-FO2-1 Exam dumps please
Anonymous
upvote

Parsad commented on June 04, 2023
Thank you for the buy 1 get 1 free discount. This helped me a lot. I donot have a lot of money.
INDIA
upvote

Petros commented on May 01, 2023
I could not have passed my certification test without the help of this study guide - highly recommend it!
PORTUGAL
upvote

Bobby commented on January 18, 2022
Passed easily.
UNITED STATES
upvote

Santosh commented on January 29, 2020
Passed my exam today with a score of 798. This is good material.
INDIA
upvote

Arron commented on January 26, 2020
This saved me so much time. The questions and answers are adequate and close to real exam. I like the PDF and its format. Just put it on my iPad and studied while traveling to work. This was my first time using this site and I am pretty happy about their service and price.
GERMANY
upvote

Suresh commented on April 17, 2019
This download is a waste of time . I downloaded the windows app and installed and it is asking to load the test. No documentation provided on how to use the desk top tool. Unable to install on my MAC not Iphone compatible. RE- Admin: Suresh, our website clearly says that the Test Engine software is for Windows only. We have not advertised anywhere in our website saying the Test Engine Software is for MAC as well.
UNITED STATES
upvote