You are documenting your organization's change control procedures for project management. What portion of the change control process oversees features and functions of the product scope?

  1. Configuration management
  2. Product scope management is outside the concerns of the project.
  3. Scope change control system
  4. Project integration management

Answer(s): A



Which of the following enables an inventor to legally enforce his right to exclude others from using his invention?

  1. Spam
  2. Patent
  3. Artistic license
  4. Phishing

Answer(s): B



Which of the following are the major tasks of risk management? Each correct answer represents a complete solution. Choose two.

  1. Assuring the integrity of organizational data
  2. Building Risk free systems
  3. Risk control
  4. Risk identification

Answer(s): C,D



Which of the following statements best describes the consequences of the disaster recovery plan test?

  1. If no deficiencies were found during the test, then the test was probably flawed.
  2. The plan should not be changed no matter what the results of the test would be.
  3. The results of the test should be kept secret.
  4. If no deficiencies were found during the test, then the plan is probably perfect.

Answer(s): A