You are a project manager of a large construction project. Within the project you are working with several vendors to complete different phases of the construction. Your client has asked that you arrange for some of the materials a vendor is to install next week in the project to be changed. According to the change management plan what subsystem will need to manage this change request?

  1. Cost
  2. Resources
  3. Contract
  4. Schedule

Answer(s): C



Which of the following roles is responsible for review and risk analysis of all contracts on a regular basis?

  1. The Configuration Manager
  2. The Supplier Manager
  3. The Service Catalogue Manager
  4. The IT Service Continuity Manager

Answer(s): B



In which of the following SDLC phases is the system's security features configured and enabled, the system is tested and installed or fielded, and the system is authorized for processing?

  1. Initiation Phase
  2. Development/Acquisition Phase
  3. Implementation Phase
  4. Operation/Maintenance Phase

Answer(s): C



Which of the following laws or acts, formed in Australia, enforces prohibition against cyber stalking?

  1. Malicious Communications Act (1998)
  2. Anti-Cyber-Stalking law (1999)
  3. Stalking Amendment Act (1999)
  4. Stalking by Electronic Communications Act (2001)

Answer(s): C



Which of the following response teams aims to foster cooperation and coordination in incident prevention, to prompt rapid reaction to incidents, and to promote information sharing among members and the community at large?

  1. CSIRT
  2. CERT
  3. FIRST
  4. FedCIRC

Answer(s): C



Viewing page 12 of 45
Viewing questions 56 - 60 out of 218 questions


Post your Comments and Discuss ISC CISSP-ISSMP exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!