Exhibit:



Which of the benefits displayed in the exhibit are MOST likely to be achieved by using test tools?

  1. ii and iv
  2. ii and iii
  3. i and iv
  4. i and iii

Answer(s): C



Which of the following is a MAJOR task of test planning?

  1. Scheduling test analysis and design tasks.
  2. Initiating corrective actions.
  3. Monitoring progress and test coverage.
  4. Measuring and analyzing results.

Answer(s): A



Which of the types of defects that are displayed in the exhibit use case testing MOST LIKELY to uncover?
i)Defects in the process flow during real-world use of the system.
ii)Defects in the interface parameters in integration testing.
iii)Integration defects caused by the interaction and interference of different components.
iv)Defects in the system as it transitions between one state and another.

  1. ii, iii
  2. i, iii
  3. iii, iv
  4. i, ii

Answer(s): B



When should configuration management procedures be implemented?

  1. During test planning.
  2. During test analysis.
  3. During test execution.
  4. When evaluating exit criteria

Answer(s): A