ITIL ISEB-SWT2 Exam
ISTQB-ISEB Certified Tester Foundation Level (Page 5 )

Updated On: 9-Feb-2026
View Related Case Study

Which list of levels of tester independence is in the correct order, starting with the most independent first?

  1. Tests designed by the author; tests designed by another member of the development team; tests designed by someone from a different company.
  2. Tests designed by someone from a different department within the company; tests designed by the author; tests designed by someone from a different company.
  3. Tests designed by someone from a different company; tests designed by someone from a different department within the company; tests designed by another member of the development team.
  4. Tests designed by someone from a different department within the company; tests designed by someone from a different company; tests designed by the author.

Answer(s): C

Explanation:

This option has someone nearer to the written code in each statement. All other options are not in this order.



View Related Case Study

Which of the following is in the correct order (typically)?

  1. Unit testing, system testing, acceptance testing, maintenance testing.
  2. System testing, unit testing, acceptance testing, maintenance testing.
  3. Acceptance testing, system testing, maintenance testing, unit testing.
  4. Unit testing, maintenance testing, system testing, acceptance testing.

Answer(s): A



View Related Case Study

Which TWO of the review types below are the BEST fitted (most adequate) options to choose for reviewing safety critical components in a software project? Select 2 options.

  1. Informal review.
  2. Management review.
  3. Inspection.
  4. Walkthrough
  5. Technical Review

Answer(s): C,E



View Related Case Study

Incidents would not be raised against

  1. Requirements
  2. Documentation
  3. Test cases
  4. Improvements suggested by users

Answer(s): D



View Related Case Study

The cost of fixing a fault:

  1. Is not important
  2. Increases as we move the product towards live use
  3. Decreases as we move the product towards live use
  4. Is more expensive if found in requirements than functional design
  5. Can never be determined

Answer(s): B






Post your Comments and Discuss ITIL ISEB-SWT2 exam prep with other Community members:

Join the ISEB-SWT2 Discussion