You make use of planning optimization in Dynamics 365 Supply Chain Management, with automatic firming enabled.

As a result of certain planned purchase orders not firming according to plan, inventory planners have to process planned purchase orders manually.

You want to make sure that the planned purchase orders are incorporated in automatic firming.
You configure the Automatic firming time fence (days).

Does the action achieve your objective?

  1. Yes, it does
  2. No, it does not

Answer(s): A



You make use of planning optimization in Dynamics 365 Supply Chain Management, with automatic firming enabled.

As a result of certain planned purchase orders not firming according to plan, inventory planners have to process planned purchase orders manually.

You want to make sure that the planned purchase orders are incorporated in automatic firming.
You configure the Lead Time.

Does the action achieve your objective?

  1. Yes, it does
  2. No, it does not

Answer(s): A


Reference:

https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning-optimization/planning-optimization-auto-firming



SIMULATION
You work for a manufacturing firm that makes use of a Dynamics 365 Supply Chain Management system.

You have been tasked with making sure that inventory of certain finished good items never reaches critically low levels. You also want production orders to be created automatically when inventory reaches a specific level.

Access the Dynamics 365 portal to achieve this goal.

  1. See Explanation section for answer.

Answer(s): A

Explanation:

Create a new safety stock journal name
1. In the Navigation pane, go to Master planning > Setup > Safety stock journal names.
2. Click New.
3. In the Name field, type 'Material'.
4. In the Description field, type 'Material'.
5. Close the page.

Create a safety stock journal
1. In the Navigation pane, go to Master planning > Master planning > Run > Safety stock calculation.
2. Click New.
3. In the Name field, enter or select a value. Select the safety stock journal name that you created, for example, Material.
4. Click Create lines.
5. In the From date field, enter a date.
6. In the To date field, enter a date.
7. Click OK. This will create lines for the dimensions that have inventory transactions.

Calculate proposal
1. Click Calculate proposal.
2. Select the Use average issue during lead time option.
3. Set Multiplication factor to '10'. The Multiply factor is used to adjust the proposal. Because demo data only has a few transactions, you will need to set the factor to get a realistic proposal.
4. Click OK. Scroll down to find M0002 and M0003. View the Calculated minimum quantity column.

Update minimum quantity
1. In the New minimum quantity field, enter a number. Update the New minimum quantity to match the value in the Calculated minimum quantity. If the Calculated minimum is zero, you can enter the desired future value. For example, you can enter the Calculated minimum quantity in this field for M0002 that has warehouse 12.
2. In the list, find and select the desired record. For example, you can select M0002 that has warehouse 12.
3. In the New minimum quantity field, enter a number. Update the New minimum quantity to match the value in the Calculated minimum quantity. If the Calculated minimum is zero you can enter the desired future value.


Reference:

https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/use-safety-stock-journal-update-minimum-coverage



You are making use of planning optimization in Dynamics 365 Supply Chain Management.

When a planning optimization job, which is configured with the wrong runtime filters, is accidentally triggered from the user interface, you are tasked with fixing the problem.

Which of the following actions should you take?

  1. You should access the plan history to cancel the job.
  2. You should access the dialog box to cancel the job.
  3. You should access the plan history to rectify runtime filters.
  4. You should access the dialog box to rectify runtime filters.

Answer(s): A


Reference:

https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning-optimization/cancel-planning-job