Which of the following documents are NOT part of the PTA handover from Sales to Delivery?

  1. Cost baseline.
  2. Project management/delivery plan.
  3. Logistics plan.
  4. WBS structure.

Answer(s): D



Which of the following is not chargeable work?

  1. Project management.
  2. Construction works.
  3. Site logistics.
  4. Account management.

Answer(s): D



What does it mean if schedule performance index (SPI) is greaterthan 1?

  1. Good progress as the project is ahead of schedule.
  2. Cost overrun as the rollout is ahead of schedule.
  3. Cost saving as the project will finish earlier.
  4. Deviations in the rollout are negatively impacting the accuracy of the cost forecast.

Answer(s): A



Before which approval gate do you have greatest possible influence on risks and the related costs?

  1. Gate 4.
  2. Gate 5.
  3. Gate 6.
  4. Project Closing.

Answer(s): A