QUESTION: 1
You can generate and manage work order exceptions in Oracle Manufacturing Cloud. Which
users can report production exception and who gets notified after an exception is raised?

A. The Production Operator can report and exception and the application generates a
notification that is sent to all users who have access to the manufacturing plant.
B. The Production Operator can report an exception and the application generates a notification
that is sent to all users with the role of production supervisor who have access to the
manufacturing plant.
C. The Production Operator or Manufacturing Engineer can report an exception and notifies the
production supervisor using Oracle Social Network since there is no system generated
notification.
D. The Production Operator can report an exception and notifies the production supervisor
using Oracle Social Network since there is no system-generated notification.

Answer(s): B
QUESTION: 2
One of the key execution capabilities that Oracle Manufacturing Cloud offers is that you can
generate and manage work order exceptions.
Which option shows the production exception types that can be reported by the production
operator?

A. Work Area, Work Center, and Resources
B. Work Center and Resources
C. Resources and Components
D. Work Area, Work Center, Resources, and Components
E. Work Area, Work Center, Resources, Components, and Miscellaneous

Answer(s): C
QUESTION: 3
Identify two reports that provide work order cost-related information to the costing user.

A. Work order Operational Analysis
B. WIP Balance by Plant
C. Purchase Variance Summary
D. Cost Accounting Dashboard

Answer(s): A, D
QUESTION: 4
A plant runs 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment
resource R1 is assigned to each of the three shifts. On a specific work order, the resource R1 is
required to work for 2 hours. The resource is set up with an efficiency of 50% and utilization of
100%. R1 is scheduled to start on the given work order at noon.
What time wil R1 be scheduled to finish, assuming no calendar exceptions have been set?