XYZ Corporation wants to ensure that every attempt by a developer to check a rule into a certain ruleset version is reviewed before that rule is allowed to be checked in. The rule should be automatically sent back to the developer without being checked in if all warnings are not justified and the fields on the history tab are not complete.
How do you address this requirement?

  1. Prior to the first assignment in the ApproveRuleCheckin flow, add a decision shape where one output connector is equivalent to the submitting the SendBack flow action.
  2. Implement a CheckForCustomWarnings activity for each rule included in the requirement. The activity issues a warning whenever the requirement's history tab criteria are not met.
  3. Override the FindReviewers decision tree to invoke a when rule that evaluates the criteria, if the when rule returns true, the decision tree returns SendBack.
  4. Override the SendBack Flow Action adding a pre-ctivity that transfers the assignment to the create operator if the rule's criteria are not met.

Answer(s): A



You manage a 30-person development team with members located across the globe. Which Pega Cloud environment best supports the needs of your team?

  1. Large sandbox
  2. Standard sandbox
  3. Large development instance
  4. Preproduction instance

Answer(s): C



Client XYZ Corp implemented Pega Customer Service.

A customer service representative (CSR) needs to launch multiple applications to manually update information to keep dam synchronized across systems. The applications are built in different technologies, decreasing the CSR's efficiency in handling customer requests. The client has a requirement to launch all applications from the PLCJA Customer service application. The client requires that data Mows to and from the Pega Customer Service application to the other applications used by the CSR. Changes made in any one of the systems is reflected in other relevant systems.
This results in the CSR handling customer requests more efficiently and spending less time manually updating dependent applications.

Which Pega capability do you recommend to support this requirement?

  1. Use Robotic Desktop Automation.
  2. Use SOAP/REST services to update the information.
  3. Use SQL connectors to update the data.
  4. Use Robotic Process Automation.

Answer(s): D



DRAG DROP (Drag and Drop is not supported)
BigCo is planning an update to JVM settings on all production nodes at the of the month. The production application supports high availability.

To ensure that users can continue working without distribution while the JVM changes are in process, select and move all of the following tasks to the Task List Order column arrange then correct order.

  1. See Explanation section for answer.

Answer(s): A

Explanation:



Page 6 of 38



Post your Comments and Discuss Pegasystems PEGAPCLSA86V2 exam with other Community members:

Vasanth commented on August 15, 2024
well documented
UNITED STATES
upvote

Shanth commented on August 15, 2024
This PDF document for this is well documented. I bought that because I wanted to print and study from hard copy.
UNITED STATES
upvote