Which task will be carried out while performing the 'identify - risks' step?

  1. Calculating when an identified risk is likely to occur
  2. Ranking the importance of the stakeholders involved in the activity
  3. Ensuring that all participants agree on the identified risks
  4. Developing an appropriate response to the identified risks

Answer(s): C



Identify the missing word in the following sentence. The impact of risks to organizational goals at the [ ? ] perspective may only become noticeable far into the future.

  1. strategic
  2. programme
  3. project
  4. operational

Answer(s): A



Which is NOT a recommended risk response option for an 'opportunity'?

  1. Enhance
  2. Transfer
  3. Share
  4. Reduce

Answer(s): D



Which is a purpose of the 'risk management policy'?

  1. Explain the actions required to implement risk management
  2. Define the Specific risk management activities that will be performed for an activity
  3. Describe how risk management practices will be implemented throughout an organization
  4. Record information about threats and opportunities for an organizational activity

Answer(s): C



Page 6 of 36



Post your Comments and Discuss PEOPLECERT MOR exam with other Community members:

Tam commented on April 27, 2024
Very nice mock exam
UNITED KINGDOM
upvote

SavvySurfer commented on June 14, 2022
These notes are very helpful in passing the exam.
UNITED STATES
upvote