Which of below sentences describes Project Brief?

  1. List of all projects that will be part of programme
  2. Control framework for programme
  3. Control framework for projects
  4. Describes purpose, cost, time, performance requirements and constraints of a project

Answer(s): D



Which of following is not responsibility of Programme Office?

  1. Repository of programme information
  2. Providing regular updates on progress to SRO
  3. Risk and Issue tracking
  4. Ensuring the control and management frameworks are effectively implemented

Answer(s): B



For a business transformation programme, which of scenarios will lead to high probability of success?

  1. Process change affecting technology and structures
  2. New products or services
  3. Internal, external and customer behavior
  4. Changing historical work practices

Answer(s): A



For a programme that focuses on Political and societal change which scenario will lead to lower probability of success?

  1. New legislation reacting to societal trends
  2. Change to current legislation
  3. Changes to public service delivery model
  4. Long term societal effects

Answer(s): D



Which document is created from Programme mandate and works as input for Business Case?

  1. Programme preparation plan
  2. Blueprint
  3. Programme Brief
  4. Programme management plan

Answer(s): C