Free P3O Foundation Exam Exam Braindumps (page: 3)

Page 2 of 38

Where may standard techniques for a P3O exist in an organization?

  1. Reported in management dashboards
  2. Within a Business Case
  3. As part of the P3O implementation plan
  4. Within corporate standards and policies

Answer(s): D



Which is a key activity of the Identify' process in the permanent P3O lifecycle?

  1. Delivering the new capability
  2. Planning tranches of delivery
  3. Analysing stakeholders and planning communications
  4. Assessing the current state of P3O provision

Answer(s): D



Which role is responsible for developing a Portfolio Dependencies Register?

  1. Programme Specialist
  2. Portfolio Analyst
  3. Reporting
  4. Tools Expert

Answer(s): B



Which is an activity in the definition and implementation of a temporary Programme Office?

  1. Create a Vision Statement for the office
  2. Transfer the realization of benefits to the operational environment
  3. Identify existing processes defined by the COE that may used
  4. Design the future state Blueprint

Answer(s): C






Post your Comments and Discuss PEOPLECERT P3O Foundation Exam exam with other Community members:

P3O Foundation Exam Discussions & Posts