The architecture of a product is usually proven in which phase of a project?

  1. Elaboration
  2. Construction
  3. Inception
  4. Transition

Answer(s): B



True or False: Governance is not a critical issue in DA projects because most of the teams are self- organizing.

  1. True
  2. False

Answer(s): B



Which of the following is not one of the reasons that Disciplined Agile teams practice transparency?

  1. Everybody knows what is happening
  2. It improves team morale
  3. It delays breaking bad news to customers
  4. Customers appreciate and expect transparency

Answer(s): C



True or False: A disciplined agile team will spend a considerable amount of time in the beginning to lock down the architecture and design of the product

  1. True
  2. False

Answer(s): B



Page 26 of 49



Post your Comments and Discuss PMI DASSM exam with other Community members:

Jack Bui commented on July 09, 2024
Helpful with me
VIET NAM
upvote

vidhya commented on July 05, 2024
it is really helpful
UNITED STATES
upvote