Which of the following would be most likely to assist when a customer has difficulty prioritizing stories?

  1. Split the stories into smaller ones to allow the customer to choose the pieces that they want.
  2. Have the team provide guidance into where their priorities lie to the customer.
  3. Provide additional technical details to give the customer insight into technical challenges.
  4. Have the team rewrite the stories with additional details to clarify requirements.

Answer(s): A



A project team is distributed across multiple countries, and they are having issues agreeing on what is being delivered and how it should be developed.Which of the following should the project manager do to alleviate some of the tension between team members, break down cultural barriers, and improve communication?

  1. Ask the team to communicate only through email to clearly document issues.
  2. Discuss this issue with senior management and recommend that the team be co- located.
  3. Monitor performance and discuss the issues in detail at the next retrospective.
  4. Hold daily standup meetings with the two teams at a time that works best for everyone.

Answer(s): D



During which activity is the sequence of numbers 0, 1, 2, 3, 5, 8, 13 often used?

  1. Denoting development sequence
  2. Estimating development hours
  3. Indicating priority of a story
  4. Estimating points of a story

Answer(s): C



Team A is producing 61 points per iteration and Team B is producing 20 points per iteration.Team A has more senior engineers.
A manager demands that Team B match Team A's points in the next iteration.
Based on this information, it is reasonable to tell the manager that:

  1. it is impossible to compare two separate teams on points alone.
  2. Team B's points will match Team A if Team B gets more senior engineers.
  3. Team B must have help self-organizing so their points match Team A.
  4. Team B's points will increase if the Product Owner becomes more involved.

Answer(s): A