You work as a project manager for BlueWell Inc.
Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team?

  1. Project Schedule Management Plan
  2. Project Staffing Management Plan
  3. Project Human Resources Management Plan
  4. Project Communications Management Plan

Answer(s): B

Explanation:

The project staffing management plan will define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team.
The staffing management plan is part of human resources plan. It is a subsidiary plan of the overall

project management plan and defines
when project team members will be brought onto and released from the project. It describes when and how human resource requirements
will be met. Depending upon the needs of the project, it can be formal or informal, highly detailed or broadly framed. The staffing management
plan may include the following items: Staff acquisition, resource calendars, staff release plan, training needs, recognition and rewards,
compliance, and safety.

Answer option D is incorrect. The communications management plan defines project communication requirements and expectations.

Answer option C is incorrect. This is not a valid project management plan.


Answer option A is incorrect. The project schedule management will define when resources are needed and scheduled. But it will not define how resources are allowed to be released from the project.



Bonnie is the project manager for her organization. She is developing a strategy to manage the project stakeholders. She wants to identify the key stakeholders, their influence over the project, their interest in project, and an assessment of methods.
What can Bonnie create to gain support from the stakeholders in her project?

  1. Stakeholder identification tools
  2. Expert judgment
  3. Stakeholder Analysis Matrix
  4. Communications management plan

Answer(s): C

Explanation:

A stakeholder analysis matrix is a simple table that identifies stakeholders, their attitude towards the project, their perceived threats and concerns, and strategies the project manager can use to gain stakeholder support and remove obstacles.

Answer option A is incorrect. Stakeholder identification tools are not a precise answer for this question.

Answer option D is incorrect. The communications management plan is a broad plan and may reference the stakeholder analysis matrix, but it
is not the best answer for this question.

Answer option B is incorrect. In some cases the project manager could rely on expert judgment, but in all projects the project manager can
use a stakeholder analysis matrix.



You are the project manager for your organization. Your project will need four electrical engineers

for the project though there are no electrical engineers within your department. This scenario is best described as which one of the following terms?

  1. Assumption
  2. Risk
  3. Resource requirement
  4. Resource constraint

Answer(s): C

Explanation:

This is an example of a resource requirement. The project needs four electrical engineers even though the resources are not within your department. Your organization could be a matrix structure, or it could hire resources from outside the organization.
Answer option D is incorrect. A resource constraint is evident when the project requires the electrical engineer and she is not available. A
requirement, as in this scenario, is simply the identification of the needed resource even if the resource is not available in your department.

Answer option B is incorrect. This is not an example of a risk, unless the resource is constrained by other projects, schedules, or work and may
not be available at all when needed.

Answer option A is incorrect. An assumption would be believing the resource is available for the project without confirming the availability of
the resource.



Vicky is the project sponsor of Robert's project. She has requested several changes for the project scope and these changes have, of course, been approved. Robert needs to incorporate the project scope changes into the activity list. Where else should Robert reflect these project changes?

  1. Project final report
  2. Scope baseline
  3. Quality control mechanism
  4. Cost baseline

Answer(s): B

Explanation:

All scope changes should also be updated in the project scope baseline. The scope baseline is the project scope statement, work breakdown structure (WBS), and the WBS dictionary.
Answer option D is incorrect. If the changes affect cost then the cost baseline would also be updated. The question did not indicate that
therbe would a change in the project cost.

Answer option C is incorrect. Quality control does not change. It always reflects the demands of the project scope.


Answer option A is incorrect. The project final report evaluates the success and failures of the project scope.