Jenny is the project manager of the NHJ Project for her company. She has identified several positive risk events within the project and she thinks these events can save the project time and money. You, a new team member wants to know that how many risk responses are available for a positive risk event. What will Jenny reply to you?

  1. Four
  2. Three
  3. Seven
  4. Acceptance is the only risk response for positive risk events.

Answer(s): A



You are working with Anna on your project to determine and map the probability distributions of risk within the project. You have indicated that you will use the uniform distribution method for a portion of the project. Which part of your project is most likely to have a uniform risk distribution?

  1. Late completion stages of a project
  2. Project phases that deal with "cutover" technologies
  3. Early concept stage of design
  4. Project initiating

Answer(s): C



You are the project manager of the GYH project for your organization. Management has asked you to begin identifying risks and to use an information gathering technique. Which one of the following risk identification approaches is an information gathering technique?

  1. Root cause analysis
  2. Assumptions analysis
  3. SWOT analysis
  4. Documentation reviews

Answer(s): A



Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?

  1. Harry is correct, because the risk probability and impact considers all objectives of the project.
  2. Harry is correct, the risk probability and impact matrix is the only approach to risk assessment.
  3. Sammy is correct, because organizations can create risk scores for each objective of the project.
  4. Sammy is correct, because she is the project manager.

Answer(s): C



Page 2 of 111



Post your Comments and Discuss PMI RMP exam with other Community members:

Doroze commented on August 04, 2024
I passed this exam today. This exam is very tough. You need to know your topics and have the full set of these questions. Or else you won't be able to pass.
Anonymous
upvote