You are preparing to start the qualitative risk analysis process for your project. You will be relying on some organizational process assets to influence the process. Which one of the following is NOT a probable reason for relying on organizational process assets as an input for qualitative risk analysis?

  1. Studies of similar projects by risk specialists
  2. Risk databases that may be available from industry sources
  3. Review of vendor contracts to examine risks in past projects
  4. Information on prior, similar projects

Answer(s): C



You work as a project manager for BlueWell Inc. You want to create a visual diagram, which can depict the resources that will be used within the project. Which of the following diagrams will you create to accomplish the task?

  1. Roles and responsibility matrix
  2. Work breakdown structure
  3. Resource breakdown structure
  4. RACI chart

Answer(s): C



Examine the figure given below.


What will be the expected monetary value of Risk C?

  1. -$113,750
  2. $175,000 if the risk event actually happens
  3. -$175,000
  4. -$27,000

Answer(s): D



John is the project manager of the NHQ Project for his company. His project has 75 stakeholders, some of which are external to the organization. John needs to make certain that he communicates about risk in the most appropriate method for the external stakeholders. Which project management plan will be the best guide for John to communicate to the external stakeholders?

  1. Risk Response Plan
  2. Risk Management Plan
  3. Communications Management Plan
  4. Project Management Plan

Answer(s): C



Page 4 of 111



Post your Comments and Discuss PMI RMP exam with other Community members:

Doroze commented on August 04, 2024
I passed this exam today. This exam is very tough. You need to know your topics and have the full set of these questions. Or else you won't be able to pass.
Anonymous
upvote