Free RMP Exam Braindumps (page: 6)

Page 6 of 111

You are the project manager of the NHJ project for your company. This project has a budget at completion of $1,650,000 and you are 60 percent complete. According to the project plan, however, the project should be 65 percent complete. In this project you have spent $995,000 to reach this point of completion. There is a risk that this project may be late so you have taken some measures to recover the project schedule. Management would like to know, based on current performance, what the estimate at completion for this project will be.
What is the estimate at completion?

  1. $1,650,000
  2. $1,666,667
  3. $663,333
  4. -$8,333

Answer(s): B



Frank is the project manager of the NHQ project for his company. Frank is working with the project team, key stakeholders, and several subject matter experts on risks dealing with the new materials in the project. Frank wants to utilize a risk analysis method that will help the team to make decisions in the presence of the current uncertainty surrounding the new materials. Which risk analysis approach can Frank use to create an approach to make decisions in the presence of uncertainty?

  1. Monte Carlo Technique
  2. Qualitative risk analysis process
  3. Quantitative risk analysis process
  4. Delphi Technique

Answer(s): C



You are a risk auditor for your company. You are reviewing the contract types a project manager has used in her project. Of the following, which contract type has the most risk for the project manager as a buyer?

  1. Cost plus percentage of costs
  2. Time and material
  3. Cost plus incentive fee
  4. Fixed-price, incentive fee

Answer(s): A



Jane is the project manager of the GBB project for her company. In the current project a vendor has offered the project a ten percent discount based if they will order 100 units for the project. It is possible that the GBB Project may need the 100 units, but the cost of the units is not a top priority for the project. Jane documents the offer and tells the vendor that they will keep the offer in mind and continue with the project as planned. What risk response has been given in this project?

  1. Acceptance
  2. Enhance
  3. Exploiting
  4. Sharing

Answer(s): A



Page 6 of 111



Post your Comments and Discuss PMI RMP exam with other Community members:

Doroze commented on August 04, 2024
I passed this exam today. This exam is very tough. You need to know your topics and have the full set of these questions. Or else you won't be able to pass.
Anonymous
upvote