You are project manager for ABD project. You, with your team, are working on the following activities:
-Probabilistic analysis of a project.
-Probability of achieving cost and time objectives.
-Trends in Qualitative Risk Analysis results.
On which of the following processes are you working on?
- Plan Risk Management
- Perform Quantitative Risk Analysis
- Perform Qualitative Risk Analysis
- Identify Risks
Reveal Solution Next Question