Tracy is the project manager of the NLT Project for her company. The NLT Project is scheduled to last 14 months and has a budget at completion of $4,555,000. Tracy's organization will receive a bonus of $80,000 per day that the project is completed early up to $800,000. Tracy realizes that there are several opportunities within the project to save on time by crashing the project work. Crashing the project is what type of risk response?

  1. Transference
  2. Mitigation
  3. Exploit
  4. Enhance

Answer(s): D



Which risk response is acceptable for both positive and negative risk events?

  1. Transferring
  2. Acceptance
  3. Sharing
  4. Enhancing

Answer(s): B



Which one of the following is the only output for the qualitative risk analysis process?

  1. Enterprise environmental factors
  2. Project management plan
  3. Risk register updates
  4. Organizational process assets

Answer(s): C



Jeff, a key stakeholder in your project, wants to know how the risk exposure for the risk events is calculated during quantitative risk analysis. He is worried about the risk exposure which is too low for the events surrounding his project requirements. How is the risk exposure calculated?

  1. The risk exposure of a risk event is determined by historical information.
  2. The probability of a risk event times the impact of a risk event determines the true risk exposure.
  3. The probability of a risk event plus the impact of a risk event determines the true risk exposure.
  4. The probability and impact of a risk event are gauged based on research and in-depth analysis.

Answer(s): B



Page 8 of 111



Post your Comments and Discuss PMI RMP exam with other Community members:

Doroze commented on August 04, 2024
I passed this exam today. This exam is very tough. You need to know your topics and have the full set of these questions. Or else you won't be able to pass.
Anonymous
upvote