There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and controlling?

  1. Work Performance Information
  2. Project management plan
  3. Risk register
  4. Change requests

Answer(s): D



A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?

  1. Exploit
  2. Mitigation
  3. Transference
  4. Avoidance

Answer(s): C



You work as a project manager for BlueWell Inc. You are working with your team members on the risk responses in the project. Which risk response will likely cause a project to use the procurement processes?

  1. Exploiting
  2. Mitigation
  3. Sharing
  4. Acceptance

Answer(s): C



During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?

  1. Cost of the project
  2. Risk rating
  3. Warning signs
  4. Symptoms

Answer(s): A



Which of the following processes is described in the statement below? "This is the process of numerically analyzing the effect of identified risks on overall project objectives."

  1. Identify Risks
  2. Perform Quantitative Risk Analysis
  3. Monitor and Control Risks
  4. Perform Qualitative Risk Analysis

Answer(s): B



Viewing page 13 of 90
Viewing questions 61 - 65 out of 273 questions