You work as a project manager for BlueWell Inc. You have to communicate the causes of risk events to the stakeholders. Which risk diagramming technique you will use to communicate the causes of risk events to project stakeholders?

  1. Project network diagrams
  2. Process flow charts
  3. Ishikawa diagrams
  4. Influence diagrams

Answer(s): C



Wendy is about to perform qualitative risk analysis on the identified risks within her project. Which one of the following will NOT help Wendy to perform this project management activity?

  1. Project scope statement
  2. Risk management plan
  3. Risk register
  4. Stakeholder register

Answer(s): D



Frances is the project manager of a project in her organization. This project has a budget of $567,000 and is schedule to last for three years. Frances wants to examine the risk events to determine which risk events have the most potential impact on the project. Which modeling technique can help Frances to accomplish this goal?

  1. Expected monetary value
  2. Sensitivity analysis
  3. Quantitative risk analysis
  4. Modeling and simulation

Answer(s): B



You are the project manager for BlueWell Inc. You are reviewing the risk register for your project. The risk register provides much information to you, the project manager and to the project team during the risk response planning. All of the following are included in the risk register except for which item?

  1. Network diagram analysis of critical path activities
  2. Symptoms and warning signs of risks
  3. List of potential risk responses
  4. Trends in qualitative risk analysis results

Answer(s): A



You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis

process except for which one?

  1. Stakeholder register
  2. Project scope statement
  3. Risk management plan
  4. Risk register

Answer(s): A



Viewing page 40 of 90
Viewing questions 196 - 200 out of 273 questions