The team member collating the list of customers has now forecast that it will NOT be complete by the end of this stage as originally planned, due to a number of new prospective customers' details not yet being available. What action should the team member take?

  1. Report the forecast delay in the next Checkpoint Report to the Executive.
  2. Add the product to the next Stage Plan in order to allocate additional resources and complete the work.
  3. Make an entry in the Risk Register so the Project Manager can decide on appropriate action.
  4. Raise an issue to inform the Project Manager.

Answer(s): D



View Related Case Study

HOTSPOT (Drag and Drop is not supported)
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement For each line identify the appropriate option, from options 1 to 6, that applies. Each option can be used once, more than once or not at all.
Hot Area:

  1. See Explanation section for answer.

Answer(s): A

Explanation:



Which of the following is the definition for an off-specification?

  1. An issue the Project Manager needs to resolve or escalate
  2. Something forecast or currently not meeting specification
  3. A proposal for a change to a baseline
  4. A statement of concern

Answer(s): B



In which strategy would the change control process be recorded?

  1. Quality Management Strategy
  2. Configuration Management Strategy
  3. Risk Management Strategy
  4. Communication Management Strategy

Answer(s): B