What do acceptance criteria identify?

  1. The approach that will be used to prove whether the project's products have been completed
  2. A measureable improvement resulting from a project outcome
  3. The measureable definitions of the attributes for a set of products to be acceptable to key stakeholders
  4. The project controls set up during the process Initiating a Project

Answer(s): C



What theme provides all management levels within the project management team with mechanisms for monitoring and control?

  1. Progress
  2. Change
  3. Organization
  4. Quality

Answer(s): A



Which is a responsibility of a Team Manager?

  1. Producing Highlight Reports for the Project Manager
  2. Reviewing the status of the stage
  3. Setting Work Package tolerances
  4. Ensuring delivery of products in the Managing Product Delivery process

Answer(s): D



Identify the missing word in the following sentence: A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.

  1. Change
  2. Plans
  3. Progress
  4. Risk

Answer(s): C