You are implementing the Design Document for a large Enterprise Revenue Cloud project having multiple lookup price rules supporting a complex pricing requirement in the Build phase. During construction the customer discovers additional logic and external data stores that need to be incorporated in order to achieve the correct pricing in a particular set of use cases. You estimate the lookup price rules will need to be modified, additional rules will need to be created and API development will be needed. As an Implementation consultant what is the appropriate course of action that should take in this predicament?
- Communication to the customer ongoing adjustment can be made as long as we're in the build phase.
- Implement the lookup price rules immediately then review with the solution Architect.
- Communicate these changes to the project manager who will evaluate the impact to scope, timeline and budget them determine the next course of action
- Consult with the solution Architect first who will expedite the updates to the design documents, then implement the changes immediately.
- Gather more details, if it requires a low level of effort then implement immediately before starting the next sprint, Otherwise Complete on the subsequent sprint.