According to the Definition of Done, which activity must be completed for each Sprint?

  1. End-user training must be delivered
  2. The solution must be built and configured in the development system (DEV)
  3. Functionality must be released to the business
  4. Functionality must be tested in the production system (PROD)

Answer(s): B

Explanation:

B is correct because according to the Definition of Done, the solution must be built and configured in the development system (DEV) for each Sprint. This means that all user stories in the Sprint backlog must be completed, tested, and accepted by the product owner in the DEV system before moving to the next Sprint. Verified


Reference:

: SAP Activate Project Management Certification Guide, page 114



What is Scrum of Scrums?

  1. Frequent inspection of code and configuration prior to quality gates
  2. Integration meeting among the various Scrum teams
  3. Mechanism for gathering and validating requirements
  4. Alternative to regular Scrum process for smaller teams

Answer(s): B

Explanation:

B is correct because Scrum of Scrums is an integration meeting among the various Scrum teams that are working on a large-scale project. It helps to coordinate and synchronize the work across teams, resolve dependencies and issues, and share best practices and learnings. Verified


Reference:

: SAP Activate Project Management Certification Guide, page 115



What is preferred when a customer wants to keep most of their original processes and migrate to SAP S/4HANA Cloud, private edition?

  1. Mix and Match
  2. System Conversion
  3. Shell Conversion
  4. Selective Data Transition

Answer(s): C

Explanation:

Shell Conversion is preferred when a customer wants to keep most of their original processes and migrate to SAP S/4HANA Cloud, private edition. It involves creating a shell system that contains the configuration and master data of the source system, and then migrating the transactional data to the target system. Verified


Reference:

: SAP Activate Project Management Certification Guide, page 128



Which activity helps the project team identify and add user stories to the backlog?

  1. Planning the User Acceptance Testing
  2. Conducting the fit-to-standard workshop
  3. Preparing a project schedule and budget
  4. Assessing project risks and issues

Answer(s): B

Explanation:

B is correct because conducting the fit-to-standard workshop helps the project team identify and add user stories to the backlog. The fit-to-standard workshop is a process of analyzing the gaps between the customer's business requirements and the standard SAP functionality, and documenting the user stories that describe the desired outcomes and acceptance criteria. Verified


Reference:

: SAP Activate Project Management Certification Guide, page 122



What is the difference between the System Conversion and New Implementation transition paths to SAP S/4HANA?
Note: There are 2 correct answers to this question.

  1. Custom code is adjusted in System Conversion and developed in New Implementation of SAP V U S/4HANA in the Realize phase.
  2. Data is migrated in System Conversion and converted in New Implementation of SAP S/4HANA in the Realize phase.
  3. Custom code is developed in System Conversion and adjusted in New Implementation of SAP u S/4HANA in the Realize phase. 4
  4. Data is converted in System Conversion and migrated in New Implementation of SAP S/4HANA in the Realize phase.

Answer(s): A,D

Explanation:

A is correct because custom code is adjusted in System Conversion and developed in New Implementation of SAP S/4HANA in the Realize phase. In System Conversion, the existing custom code needs to be adapted to run on SAP S/4HANA. In New Implementation, new custom code needs to be developed to meet the customer's specific requirements. D is correct because data is converted in System Conversion and migrated in New Implementation of SAP S/4HANA in the Realize phase. In System Conversion, the existing data needs to be converted to the new data structures and formats of SAP S/4HANA. In New Implementation, new data needs to be migrated from the legacy system or other sources to SAP S/4HANA. Verified


Reference:

: SAP Activate Project Management Certification Guide, page 127