What activity do you perform during the daily stand-up meeting?
Answer(s): C
C is correct because reporting showstoppers is one of the activities that you perform during the daily stand-up meeting. A showstopper is an issue or impediment that prevents the team from completing their sprint goal or user story. The scrum master is responsible for resolving or escalating the showstoppers as soon as possible. Verified
: SAP Activate Project Management Certification Guide, page 115
Which of the following considerations apply when determining the project methodology? Note:There are 3 correct answers to this question.
Answer(s): A,C,D
A is correct because implementation fit is one of the considerations that apply when determining the project methodology. It means that the project methodology should match the type and scope of the implementation, such as cloud, on-premise, hybrid, or mixed scenarios. C is correct because organizational fit is one of the considerations that apply when determining the project methodology. It means that the project methodology should suit the culture and maturity of the organization, such as its readiness for change, agility, and innovation. D is correct because project fit is one of the considerations that apply when determining the project methodology. It means that the project methodology should align with the characteristics and constraints of the project, such as its size, complexity, duration, and budget. Verified
: SAP Activate Methodology for SAP S/4HANA Cloud, page 13
Your customer is using a non-SAP ERP system and decides to implement SAP S/4HAN
Answer(s): B,D,E
B is correct because New Implementation SAP S/4HANA Cloud, public edition is one of the options that are available to a customer who is using a non-SAP ERP system and decides to implement SAP S/4HANA. It involves setting up a new SAP S/4HANA Cloud system with predefined configuration and data migration from the legacy system.D is correct because New Implementation SAP S/4HANA Cloud, private edition is one of the options that are available to a customer who is using a non-SAP ERP system and decides to implement SAP S/4HANA. It involves setting up a new SAP S/4HANA Cloud system with customized configuration and data migration from the legacy system.E is correct because New Implementation SAP S/4HANA is one of the options that are available to a customer who is using a non-SAP ERP system and decides to implement SAP S/4HANA. It involves setting up a new SAP S/4HANA on-premise system with tailored configuration and data migration from the legacy system. Verified
: SAP Activate Project Management Certification Guide, page 126
Which tool do you use to configure SAP S/4HANA Cloud, public edition?
C is correct because SAP Central Business Configuration is the tool that you use to configure SAP S/4HANA Cloud, public edition. It provides a guided configuration process that helps you to activate your system, enter configuration data, and validate your settings. Verified
: Central Business Configuration Overview
Which of the following best outlines the sequence of testing in the Realize phase?
Answer(s): B
B is correct because String test > Integration Test > User Acceptance Test is the best outline of the sequence of testing in the Realize phase. The String test is performed first to verify the end-to-end processes across the system landscape. The Integration Test is performed next to verify the integration of the solution with other systems and interfaces. The User Acceptance Test is performed last to verify that the solution meets the customer's business requirements and expectations.Verified
: SAP Activate Project Management Certification Guide, page 120
Post your Comments and Discuss SAP C_ACT_2403 exam prep with other Community members:
Our website is free, but we have to fight against AI bots and content theft. We're sorry for the inconvenience caused by these security measures. You can access the rest of the C_ACT_2403 content, but please register or login to continue.