What term is used for a ready-to-run SAP S/4HANA system with pre-built solution Documentation

  1. Best practice system
  2. Fully activated appliance
  3. SAP model company
  4. SAP cloud appliance library

Answer(s): A



Which new role is introduced in the SAP activate methodology in a full scrum team?

  1. Project manager
  2. Product owner
  3. Application consultant
  4. System administrator

Answer(s): C



What are some of the key characteristics of the implementation approach in SAP Activate methodology?
There are 3 correct answers to this question.

  1. On premise only
  2. ActivaDelta-based
  3. Cloud ready
  4. Fixed scope
  5. Based on ready-to-use content

Answer(s): B,C,E



What is the purpose of a firm-up sprint?

  1. To perform string test
  2. To revise the release plan and sprint plan
  3. To run an end-to-end integration test
  4. To demonstrate functionality from previous sprints

Answer(s): A



What criterion does the product owner use to sequence the product backlog?

  1. Relative effort
  2. Resource availability
  3. Business priority
  4. Complexity

Answer(s): C