Which type of testing should be done after a release upgrade has occurred?
Answer(s): A
What are some characteristics of the SAP S/4HANA Migration Cockpit? Note: There are 2 correct answers to this question.
Answer(s): C,D
In the SAP Activate prepare phase, the cloud project is set up and officially launched. Which change management activities are usually started in this phase? Note: There are 3 correct answers to this question.
Answer(s): A,C,D
Which SAP products relate to the scenarios included in the SAP Activate roadmap for the Intelligent Enterprise? Note: There are 3 correct answers to this question.
Answer(s): A,B,C
Which of the following configuration items CANNOT be changed after the initial provisioning of SAP S/4HANA Cloud Public Edition? Note: There are 2 correct answers to this question.
Answer(s): A,D