For which documents can you configure the usage of time-dependent conditions?
Note: There are 2 correct answers to this question.

  1. Scheduling agreement
  2. Contract
  3. Purchase order
  4. Quotation

Answer(s): A,D



What are some of the consequences of setting the Delivery Completed indicator in a purchase order (PO) item?
Note: There are 2 correct answers to this question.

  1. The commitment for the PO item will increase.
  2. You can still post goods receipts of remaining quantities.
  3. The PO item CANNOT be deleted and archived.
  4. The PO item is skipped when delivery reminders are generated.

Answer(s): B,D



Which of the following procurement proposals can be created during an MRP Live planning externally procured materials?
Note: There are 2 correct answers to this question.

  1. Delivery schedule line
  2. Purchase order
  3. Planned order
  4. Purchase requisition

Answer(s): A,D



What does the account assignment category controling a purchase requisition or purchasing document item? Note; There are 2 correct answers to this question.

  1. The type of account assignment object you must specify
  2. The item categories you are allowed to use
  3. Whether you can post a goods receipt
  4. Whether you must enter a material

Answer(s): A,D



What must you do when using supplier consignment?
Note: There are 2 correct answers to this question.

  1. Create consignment info records
  2. Settle liabilities resulting from consignment stock receipts
  3. Settle liabilities resulting from consignment stock withdrawals
  4. Create consignment storage locations

Answer(s): A,C