Free SAP C_TS4CO_2020 Exam Questions (page: 7)

You are setting up costing-based Profitability Analysis for your organization. How do you configure the different market segments?

  1. As value fields
  2. As divisions
  3. As characteristics
  4. As key figures

Answer(s): C



You use a ledger, an additional standard ledger and an extension ledger. You post a general journal entry without indicating a ledger group. For which ledger(s) are separate line items posted in the universal journal?

  1. The leading and extension ledgers
  2. The standard ledgers
  3. The leading ledger only
  4. All ledgers

Answer(s): A



Which are levels of internal order planning?
There are TWO correct answers for this question.

  1. Group costing
  2. Integrated planning
  3. Overall planning
  4. Primary and secondary cost and revenue planning

Answer(s): B,C



In the product Cost by Order component, what does the system calculate depending on the order status?

  1. WIP at target costs or variances
  2. WIP at actual costs or variances
  3. WIPat planned costs or variances
  4. Both WIP and variances or only variances

Answer(s): B