You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you want to use a second sequence on other work centers for operations 30 and 40. Which sequence category do you use to create the second sequence in the system?
- Finish-start relationship
- Standard sequence
- Parallel sequence
- Alternative sequence