Which of the following is part of the Explore phase in the "New implementation od SAP S/4 HANA Cloud" transition path?

  1. Simplification and custom code impact analysis
  2. Setup and enablement
  3. Fit-to-standard
  4. Solution validation and Delta design

Answer(s): C



How can a customer get access to SAP Cloud ALM?

  1. SAP Cloud ALM fair usage rights are included in SAP Enterprise Support, cloud editions at NO additional cost
  2. SAP Cloud ALM fair usage rights are included in SAP Preferred Success and SAP Preferred Care at NO additional cost
  3. SAP Cloud ALM fair usage rights are included in SAP MayAttention and SAP ActiveAttention at NO additional cost
  4. SAP Cloud ALM can be bought on the SAP Store

Answer(s): A



What tool provides guidance on replacing custom code developed for SAP ERP with SAP S/4HANA functionality for the system conversion?

  1. Simplification item check (Si-check)
  2. Software provisioning manager
  3. SAP code inspector
  4. Software update manager with database migration option

Answer(s): A



Which activity helps the project team to add the user stories to the product backlog?

  1. Planning the User Acceptance Test
  2. Conducting the Solution Validation
  3. Assessing Project Risks
  4. Preparing a Project Schedule

Answer(s): B



In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project?

  1. Realize
  2. Deploy
  3. Prepare
  4. Explore

Answer(s): D



Viewing page 10 of 35
Viewing questions 46 - 50 out of 167 questions