What is the recommended duration of an Iteration in SAFe?

  1. Three weeks
  2. Two weeks
  3. Four weeks
  4. Six weeks

Answer(s): B



What are personas?

  1. Descriptions of actual target customers or users
  2. Key end-users the Product Owner leverages for managing the backlog
  3. Fictional representations of target customers or users

Answer(s): C



The team's draft plan review consists of which three items at the end of the first day of the Program Increment (PI) Planning event? (Choose three.)

  1. Capacity and load estimates
    (Correct)
  2. Program delivery schedule
  3. Draft PI Objectives
  4. Risks and impediments
  5. Iteration Goals
  6. Refined team backlogs

Answer(s): A,C,D



Which statement is true about nonfunctional requirements?

  1. They stay in the Portfolio Backlog until implementation capacity is available
  2. They are split into Features and acceptance criteria is established
  3. They operate as constraints on the design of the system

Answer(s): C