What is one problem with phase-gate Milestones?

  1. They assume a point Solution exists and can be built right the first time
  2. They force design decisions too late in the process
  3. They account for variability inherent in the process
  4. They require the Product Owner to act as gatekeeper or guardian of the process

Answer(s): A

Explanation:

Phase-gate milestones are traditional project management mechanisms that mark the end of one phase and the beginning of another. One major problem with phase-gate milestones is that they assume a point solution exists and can be built correctly the first time. This assumption does not account for the iterative nature of Agile methodologies, where solutions are developed incrementally and iteratively, with feedback loops and continuous improvement. Assuming a point solution can be finalized early often leads to rigidity, lack of adaptability, and higher risks of delivering a product that does not meet the actual needs or expectations.



What is one output from the problem-solving workshop?

  1. ROAMed risks
  2. All the potential Solutions the team could identify
  3. An assessment report
  4. Top improvement items for the next PI

Answer(s): D

Explanation:

One of the primary outputs from the problem-solving workshop in SAFe is identifying the top improvement items for the next Program Increment (PI). These workshops focus on analyzing issues, determining root causes, and formulating actionable improvements. By prioritizing and committing to these improvement items, teams can systematically address problems and enhance their performance and productivity in subsequent PIs.



How is average lead time measured in a Kanban system?

  1. By taking the average velocity over the last three iterations
  2. Measure the vertical distance between arrival and departure lines on a cumulative flow diagram
  3. Measure the horizontal distance between arrival and departure lines on a cumulative flow diagram
  4. Measure the lead time for at least three items and calculate the statistical mean of the items

Answer(s): C

Explanation:

In a Kanban system, average lead time is measured by observing the horizontal distance between the arrival and departure lines on a cumulative flow diagram (CFD). The CFD visualizes the flow of work items through various stages of the workflow. The horizontal distance between the points where work items enter and leave a particular stage represents the lead time. By calculating this distance over multiple items, teams can determine the average lead time, providing insights into process efficiency and areas for potential improvement.



What is the primary measurement during Inspect and Adapt?

  1. Program predictability measure
  2. Team NPS score
  3. Number of Features delivered
  4. Number of automated tests

Answer(s): A

Explanation:

The primary measurement during the Inspect and Adapt (I&A) event in SAFe is the program predictability measure. This metric assesses the Agile Release Train's (ART) ability to deliver on its commitments within a Program Increment (PI). It helps teams understand how accurately they can plan and execute work, providing a basis for continuous improvement. By focusing on predictability, organizations can improve their planning processes, align better with business objectives, and ensure more reliable delivery of value.