What is the primary purpose of the management meeting at the end of Day 1 of PI Planning?

  1. To assign business value to the teams' draft PI Objectives.
  2. To make adjustments to the PI scope and address program challenges.
  3. To design the next generation of the product.
  4. To evaluate the performance of teams.

Answer(s): B



When is the Solution Demo conducted?

  1. On demand.
  2. At the end of each Sprint.
  3. At the end of each PI.
  4. Mid-PI.

Answer(s): C



What contributes to establishing trust in SAFe?

  1. Decentralization of control.
  2. Transparency.
  3. Reporting.
  4. U-curve optimization.
  5. Servant leadership.

Answer(s): B



Vikas is a new Solution architect and is trying to understand the Solution Context.
What is the most important factor for him to consider?

  1. The acceptance Criteria for the Capabilities.
  2. Job sequencing for the Epics in the Value Stream Backlog.
  3. The Economic Framework for the Value Stream.
  4. The environment in which the Solution is deployed.

Answer(s): D



An Agile Release Train prepares for PI Planning. They have both Features and Program Epics among the desirable items for this PI. However, Product Management is stuck because some Epics are too big and won't fit in this PI.

  1. Pick only those Epics that have clearly defined success criteria and might fit into the PI.
  2. Split Epics into Features and prioritize the Features to determine what should go into the PI.
  3. Split Epics into Features and use capacity allocation to determine what should go into the PI.
  4. Instead of planning just the upcoming PI, plan for a longer period to cover the full duration of the Program Epics.

Answer(s): B