An Agile Release Train prepares for PI Planning. They have both Features and Program Epics among the desirable items for this PI. However, Product Management is stuck because some Epics are too big and won't fit in this PI.

  1. Pick only those Epics that have clearly defined success criteria and might fit into the PI.
  2. Split Epics into Features and prioritize the Features to determine what should go into the PI.
  3. Split Epics into Features and use capacity allocation to determine what should go into the PI.
  4. Instead of planning just the upcoming PI, plan for a longer period to cover the full duration of the Program Epics.

Answer(s): B



Enabler Features can contribute to the Architectural Runway and realize system Nonfunctional Requirements at the same time.

  1. True
  2. False

Answer(s): A



SAFe uses Kanban to manage flow at the Portfolio Level for the following reasons EXCEPT __________.

  1. To ensure that the analysis and discovery work needed for the items are not time bound.
  2. To ensure that there is visibility and transparency.
  3. To capture all ideas in the funnel.
  4. To limit the number of initiatives under consideration.
  5. To ensure that portfolio items are delivered to the Program or Solution Backlogs every 2 weeks.

Answer(s): E



What is the target percentage for the Program Predictability Measure?

  1. <50%
  2. 50-75%
  3. 80-100%
  4. 100%
  5. None of the above.

Answer(s): C