The Release Train Engineer is a servant leader who displays which two actions or behaviors? (Choose two.)

  1. You have reached the max number of allowed answers
  2. Establishes Feature acceptance criteria
  3. Listens and supports teams in problem identification and decision-making
  4. Identifies market needs
  5. Leads by example
  6. Owns Vision and Roadmaps, Program Backlog, and ROI

Answer(s): C,E



Product Management is responsible for "what gets built" as defined by the Vision, Roadmap, and what else?

  1. Program Backlog
  2. Key stakeholders
  3. Customers
  4. PI Planning

Answer(s): A



Which statement is true about the purpose of a work in process constraint?

  1. It encourages collaboration and enables flow
  2. It captures where all new "big" ideas come from
  3. It helps analyze, approve, and track Portfolio Epics and Enablers
  4. It identifies possible constraints for Solution completion

Answer(s): A



What is the recommended length of an Iteration?

  1. Two weeks
  2. Ten weeks
  3. Four weeks
  4. Eight weeks

Answer(s): A



What does a program board help teams identify?

  1. Program-level risks
  2. Dependencies between teams
  3. Each teams tasks
  4. Work breakdowns

Answer(s): B