On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further.
What is the PO's best course of action?

  1. Defer acceptance testing to the next Iteration
  2. Communicate the status of the Iteration to all stakeholders
  3. Have an emergency Iteration Planning meeting
  4. Stop the current Iteration and plan a new Iteration with the new knowledge

Answer(s): B



What is a major benefit of reducing batch size?

  1. Increases visibility
  2. Decreases stress on the system
  3. Increases work in process
  4. Increases throughput

Answer(s): D



Which activity happens in the Inspect and Adapt workshop?

  1. A demo of the integrated system
  2. Refining the Program backlog
  3. Planning the next PI
  4. A retrospective of the Iteration

Answer(s): A



A decrease in variability leads to an increase in what?

  1. Autonomy
  2. Options
  3. Predictability
  4. Innovation

Answer(s): C