Based on "Sprint 7 Burn-Down Chart," would you do anything different in Sprint 8? (choose the best two answers)

  1. The Developers may forecast less overall work in Sprint 8.
  2. Stakeholders will encourage the Scrum Team to estimate better during the Sprint 8 Planning Meeting.
  3. There is nothing wrong. The Developers will present all Product Backlog items selected for Sprint 7 at the end of the Sprint.
  4. The Developers carry over incomplete Sprint Backlog items from Sprint 7 to Sprint 8 and monitor the Sprint 8 burn-down chart. As soon as deviation from trends is detected, the Developers work with the Product Owner to negotiate remaining work.
  5. The Scrum Master adds additional Developers for Sprint 8.
  6. The Developers put incomplete Product Backlog items back into the Product Backlog for re- ordering. The Product Owner may ask the Developers to complete the unfinished Product Backlog items from Sprint 7 in Sprint 8.

Answer(s): A,F

Explanation:

If a burn-down chart shows issues in Sprint 7, the Developers may adjust the forecast for Sprint 8 based on learning. Incomplete items should be returned to the Product Backlog for reordering, ensuring prioritization aligns with goals.



Which of the following is required by Scrum? (choose the best answer)

  1. Sprint Retrospective
  2. Developers must stand up at the Daily Scrum.
  3. Sprint Burndown Chart.
  4. Release Planning.
  5. All of the above.

Answer(s): A

Explanation:

Scrum mandates the Sprint Retrospective to inspect and adapt. Other practices, such as burndown charts and release planning, are tools and techniques but are not required by Scrum.



When are individuals with testing and quality expertise included in the software development effort? (choose the best answer)

  1. From the beginning and throughout all Sprints.
  2. When the implementation of each feature is complete.
  3. After Sprint Review.
  4. When the product is feature complete.

Answer(s): A

Explanation:

Scrum emphasizes quality from the start. Testing and quality expertise are integral throughout all Sprints to ensure continuous feedback and integration of quality measures.



What should the Scrum Team do during the first Sprint? (choose the best answer)

  1. Analyze, describe, and document the requirements for the subsequent Sprints.
  2. Define the major product features and a release plan architecture.
  3. Make up a plan for the rest of the project.
  4. Create at least one valuable and useful Increment.

Answer(s): D

Explanation:

The first Sprint is focused on delivering a valuable and usable Increment. This embodies Scrum's iterative approach, where value is delivered early and feedback is gathered.